On construction sites, a box is not required for splices or junctions in which of the following?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 9060
- D: Multiconductor cord or cable assemblies, when using approved fittings or the circuit conductors of portable cords
Explanation
Temporary wiring rules allow splices in multiconductor cord or cable on construction sites without a box when the splice is made with approved methods. Permanent wiring methods such as concealed NM or raceway conductors still require boxes.
More questions: Special Occupancies
- 9061For temporary branch circuits during construction, Type NM cable is permitted in buildings of what height?
- 9001A room where flammable gases or vapors from flammable liquids may be present in quantities sufficient to produce an ignitible mixture is classified as which class?
- 9002A location is hazardous because of the presence of combustible dust. Which class applies under the class and division system?
- 9003A cotton gin where easily ignitible fibers are handled, but not normally suspended in the air in ignitible quantities, is generally classified as which class?
- 9004In a Class I location, what distinguishes a Division 2 area from a Division 1 area?
- 9005Under the zone system for flammable gases and vapors, which zone describes a location where ignitible concentrations are present continuously or for long periods?