Question 15056 of 790 · California General Electrician Exam
Within how many days of receiving an application must DAS inform the applicant whether they are eligible for the exam?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 15056
- B: 30 days
Explanation
8 CCR 291.2(e) requires DAS to inform the applicant in writing within 30 days of receipt whether they are eligible to test or the application is deficient.
More questions: Electrical Safety
- 15057Which certification category allows work in all California certification categories?
- 15058A California Residential Electrician may not work in which of these occupancies?
- 15059Under 8 CCR 293.0, within how many days of service of a notice to suspend or revoke certification must a hearing be requested?
- 15060What is the main purpose of grounding the frame of electrical equipment in terms of worker safety?
- 15001According to NFPA 70E, what is the preferred way to protect workers from electrical hazards before working on equipment?
- 15002Which of the following is the final step in verifying an electrically safe work condition?